A Recent Superior Court Decision May Affect Subcontractor/Supplier Mechanic’s Liens

In a recent decision, the Superior Court discharged the mechanic’s liens of several subcontractors, because the general contractor had already filed a lien for the unpaid contract balance. Wegrzyniak v. Hanley Constr., LLC, WL 5706192 (Conn. Super. Ct. Oct. 30, 2017). Insofar as any substantial construction project will involve a general contractor, subcontractors, sub-subcontractors, and suppliers, there are obviously many potential lien claimants. Nonetheless, the court said that “[f]or good reasons, the mechanic’s lien statutes don’t permit multiple liens,” and with regard to the subcontractor whose lien included a claim for extra work, the court said that “[w]ithout an agreement to support the additional work…, [the subcontractor’s] lien must be discharge.” Id. In light of the foregoing, Wegrzyniak may stand for the proposition that subcontractors, sub-subcontractors, and/or suppliers are precluded from filing mechanic’s liens when the general contractor files a mechanic’s lien covering the entire project, but, in my opinion, subcontractors, sub-subcontractors, and suppliers should continue filing their own mechanic’s liens.

To summarize the reasoning of the Wegrzyniak decision in plain English, because the court understood that the property owner should not be held liable for more than the amount it agreed to pay the general contractor,

A Mechanic’s Lien: Something Simple That’s Been Made Complicated

One of the first things I was ever taught about mechanic’s liens is that the legislation’s original intent was for a contractor to be able to perfect a mechanic’s lien without the aid of an attorney. If that’s true, the system is not working as intended. Of course, that is not surprising given the complicated legislation and its arguably inconsistent interpretation.

A mechanic’s lien is unique insofar as it allows a contractor to obtain an interest in real property without requiring any kind of hearing or notice. As long as the lien documents are properly prepared, recorded, and served, the lien is in place. In addition, the fact that mechanic’s liens have priority dates that relate back to the first day that the contractor performs work and/or supplies materials, mechanic’s liens that did not exist when a mortgage was given or the property was sold can appear on the land records after such transactions and take priority over an earlier filed mortgage and/or encumber property owned by someone who was not the property owner at the time the work was performed, materials were supplied and/or services were rendered.

Of course, reading the statutes is not sufficient to completely understand mechanic’s liens.