Understanding Unabsorbed Home Office Overhead

It is readily apparent that – if a project is delayed – the contractor is losing money.  The increased direct costs associated with the labor and equipment on site are obvious. The more complex question arises when considering the effect a delayed project has on a contractor’s recovery of its home office overhead, where “home office overhead” is defined as the cost of the contractor’s main office including, but not limited to, rent, utilities, executive and management salaries, staff, office equipment, office supplies, taxes, insurance, etc.  Everyone intuitively understands that a delayed project increases such costs in the same manner that that delays increase the project’s direct costs but increases in home office overhead cannot be directly correlated to any one project because a contractor typically has several projects with overlapping schedules underway at any given time.  Over the years, courts have attempted to determine the damages necessary “to compensate a contractor for its indirect costs that cannot be allocated to a particular contract for the period during which the government has made contractual performance impossible.”  Charles G. Williams Constr., Inc. v. White, 326 F.3d 1376, 1380-1381 (Fed. Cir. 2003).  “As a result, there are at least nine formulas that have been used,

Contractors Have Statutory Rights That They May Assert During Payment Disputes

A recurring problem in the construction industry is the failure of owners to issue timely payments.  The problem not only affects contractors but also the subcontractors and/or suppliers who have to wait for the money to pass through the project’s general contractor and/or a higher tier subcontractor.  Most contractors are aware of their right to secure payment of the monies owed through a mechanic’s lien (private work) or by filing a payment bond claim (public work or private work if applicable) but there are statutory rights of which contractors should be aware.

Connecticut General States § 42-158i defines a “construction contract” as “any contract for the construction, renovation or rehabilitation in this state on or after October 1, 1999, including any improvements to real property that are associated with such construction, renovation or rehabilitation, or any subcontract for construction, renovation or rehabilitation between an owner and a contractor, or between a contractor and a subcontractor or subcontractors, or between a subcontractor and any other subcontractor” but excludes contracts between a contractor and any local, state, or federal government, and it excludes contracts for building residential structures with less than 4 units.  Id.

According to § 42-158i,

Recent OCIP Decision Reminds Contractors About the Importance of Contract Language

In recent years, Owner Controlled Insurance Programs (“OCIP”) have become more prevalent in public and private construction projects.  An OCIP “is a class of ‘wrap-up’ insurance that provides coverage for many construction project participants under one program.”  Capstone Bldg. Corp. v. Am. Motorists Ins. Co., 308 Conn. 760, 767 (Conn. 2013).  Such programs typically include commercial general liability insurance and worker’s compensation insurance.  In general, OCIPs reduce a project’s overall cost because the owner does not have to pay the multiple layers of duplicative administration associated with the general contractor and each subcontractor having its own insurance coverage.  The general understanding is that the project owner benefits from the savings but a recent Superior Decision reminds us that contractual duties and obligations are derived from the plain language of the contract and not what may reasonably inferred.

In Elevator Serv. Co. v. Reg’l Scaffolding & Hoisting Co., 2013 Conn. Super. LEXIS 687 (Conn. Super. Ct. Mar. 27, 2013), Elevator Service Co., Inc. (“Elevator Service”) and Regional Saffolding & Hosting, Inc. (“Regional Scaffolding”) entered into an agreement pertaining to a project known as the Royal Bank of Scotland (the “Project”).  The issue before the court was whether Elevator Service had to pass along to Regional Scaffolding a discount that it received through the subject project’s OCIP. 

A Cautionary Tale for All Subcontractors

The Connecticut Appellate Court recently handed down a decision that should have all subcontractors carefully reviewing their subcontracts.  In Suntech of Connecticut, Inc. v. Lawrence Brunoli, Inc., 143 Conn. App. 581 (2013), Suntech of Connecticut, Inc. (“Suntech”) agreed to “provide glass doors, glass, glazing, an aluminum framing system, and a metal framing system” as a subcontractor on a state project.  Id.  As a result of an error in the plans and specifications, Suntech incurred substantial additional costs. Typically, when an error in the plans and specifications results in a contractor incurring additional costs, the contractor is entitled to a change order but that is not what occurred in this case.

The Suntech decision appears to go against two principles of Connecticut construction law.  First, in Southern New England Contracting Co. v. State, 165 Conn. 644, the Connecticut Supreme Court issued a decision consistent with the Spearin doctrine which states that, because the contractor agrees to build the project in accordance with the plans and specifications, the contractor will not be held responsible for damages should the plans and specifications end up being defective.  Second, while not conclusively determined,

Connecticut Statutes Provide Assistance with Receiving Prompt Payment on Public and Private Construction Projects

Under Connecticut law, an owner should pay its general contractor within 30 days of having received the general contractor’s application for payment; the general contractor, in turn, is required to pay its subcontractors and suppliers within 30 days of having received payment from the owner; and the subcontractors should then pay their sub-contractors and suppliers within 30 days of having received payment from the general contractor and so on down the line.  See Gen. Stat. § 49-41a and Conn. Gen. Stat. § 42-158j.

The provisions in § 49-41a and § 42-158j are substantially similar except that:

1.) Only private owners are required to make payment to their general contractors within a specified number of days after receiving an application for payment; and

2.) The statute only applies to public projects for which a payment bond is required, which is any public works project whose contract amount exceeds $100,000.

Both statutes also have similar enforcement procedures.  Either a subcontractor on a public project to which the statute applies or general contractors and subcontractors on a private project can make demand for payment by way of registered or certified mail and, within 10 days,

Restarting the 90 Day Clock to File a Mechanic’s Lien

As most contractors are aware, in Connecticut, you have 90 days after the last day that you supply labor and/or materials to file a mechanic’s lien.  Many other states have the same or a similar requirement pertaining to when a mechanic’s lien can be filed.  The question that is often asked is which “last day” starts the clock.

In a common scenario, additional work is performed more than 90 days after what was originally thought to be the last day worked and the contractor then claims that the second last day starts a new 90 days clock to file a mechanic’s lien.  Sometimes such mechanic’s liens are upheld but they are typically invalidated.  The reason is that the typical scenario involves a contractor – who has not been paid – realizes that his time to file a mechanic’s lien has expired so he returns to the site to perform a minor punchlist item that was inadvertently left undone initially.  Generally speaking, to restart the mechanic’s lien clock, a contractor must perform substantive work that was authorized by the owner or someone rightfully acting on the owner’s behalf.  The most recent guidance on this issue was provided by the Connecticut Appellate Court in Cianci v.

Another Step Closer to Understanding Pay-When-Paid Clauses

No provision in a standard construction contract has been more debated than the requirement for the general contractor to pay its subcontractors after its receipt of payment from the owner.  In situations where the owner does not pay the general contractor, the general contractor typically argues that it has no obligation to pay the subcontractor even if the reason for the owner’s nonpayment had nothing to do with the subcontractor.  Conversely, the subcontractor argues that – when the reason for the owner’s nonpayment is not the subcontractor’s fault – the general contractor must pay the monies the subcontractor is due.  Generally, the courts have said that contract language which states that the subcontractor shall not be paid until after the general contractor’s receipt of payment from the owner merely sets forth the time for payment and does not transfer the risk of the owner’s insolvency from the general contractor to the subcontractor.  “Normally and legally, the insolvency of the owner will not defeat the claim of the subcontractor against the general contractor.”  Sil/Carr Corp. v. Bartlett, 2012 Conn. Super. LEXIS 1665 (Conn. Super. Ct. June 26, 2012).  It is, however, possible for the contractor to transfer the risk of the owner’s nonpayment to the subcontractor. 

A Contractor That Acts as His Own Expert Witness May Inadvertently Waive Attorney Client Privilege

The general rule is that a party does not have to disclose communications with its attorney seeking legal advice.  A recent Superior Court decision, Noble v. the City of Norwalk, 2012 Conn. Super. LEXIS 2017, however, has found an exception to the attorney client privilege that contractors need to be aware about.

During a trial, witnesses are not allowed to give their opinion unless they are qualified as an “expert.”  Under the legal definition, an “expert” is anyone that has knowledge through education, training or experience that would be helpful to the jury given the subject matter of the lawsuit.  Based upon the foregoing definition, almost anyone can qualify as an expert if the right case came along.  For example, my 13-year-old daughter has been taking ballet lessons since she was 3.  If ballet ever became relevant to a key issue in a lawsuit, my daughter would qualify as an expert on that subject.

In construction litigation, there are always questions that are not clearly fact or opinion.  For example, the amount of time that the forms have to remain in place after a concrete pour is a subject upon which there is disagreement and often depends upon the structure that was poured and the conditions under which the concrete was placed. 

Don’t Get Creative When Attempting To Enforce Mechanic’s Lien Rights

In Connecticut, the law pertaining to mechanic’s liens is well settled.  You will not come across many issues of first impression while trying to enforce a mechanic’s lien and, therefore, practitioners should not attempt to drive the proverbial square peg into a round hole.  Such an attempt was made (and failed) in a matter recently decided by the Connecticut Superior Court.

In that case, an assignee of a mortgage brought a foreclosure action and named a contractor as a defendant because the contractor’s mechanic’s lien was subsequent in right to the interest being foreclosed.  Normally, if the property proceeds all the way through the foreclosure process, a contractor holding a subordinate lien allows his interest in the property to expire because the only way to maintain the lien is to pay off the foreclosing mortgage but , in this case, the contractor did not give up that easily.

Here, the contractor alleged that the assignee became the “owner” of the property by virtue of the construction mortgage and, as such, was responsible to pay for the work that the contractor performed.  The court identified 2 issues that allowed the court to dispose of the contractor’s claim on summary judgment. 

Act Promoting Fairness In Private Construction Contracts? Hardly.

A new law has recently gone into effect in Massachusetts that drastically changes the relationships between private owners, contractors and subcontractors; and some people are going to suffer severe financial hardship as a result. For some inexplicable reason, the Commonwealth of Massachusetts has decided to interfere in what has been traditionally been the private right to contract. The new law has three main points; each more insidious than the next.

First, “pay when paid” and/or “pay if paid” provisions commonly found in subcontracts are now prohibited by statute in the Commonwealth of Massachusetts. Many general contractors simply are unable to pay their subcontractors until they receive payment from the owner. Thus, they write their subcontracts to make the subcontractor’s payment due a reasonable time after the contractor receives payment from the owner. Now, “every contract for construction shall provide reasonable time periods within which” an application for payment shall be submitted, approved and paid. Contract provisions that first require that the contractor to receive payment from the owner are void except in cases where the subcontractor has performed defective work or is insolvent.

Second, general contractors must abide by the time requirements for the review and approval of pay applications or suffer an extremely harsh result.