Recent Supreme Court Case Teaches Important Lessons

It is no secret that public works construction is a difficult business.  On any given project there are innumerable ways that things can go wrong. With any project involving excavation and underground utilities, encountering changed conditions should not be a surprise.  Of course, such changed conditions are not the contractor’s responsibility.  What is the contractor’s responsibility, however, is providing the public owner with proper notice of its claims in accordance with the subject agreement.

One of the reasons public works construction projects are more onerous than their private counterparts is because public owners rarely negotiate contract terms. Contracts that are slanted significantly in the public owner’s favor are the norm.  Thus, as the contractor in a recent state Supreme Court decision learned, it is vitally important to read the contract and abide by its terms.

One of the lessons from Old Colony Cosntr., LLC v. Town of Southington, 316 Conn. 202 (Conn. April 21, 2015) is that general assertions of entitlement to damages and/or additional contract time is not sufficient when the contract requires more detail.  During the long duration of the project, the contractor in Old Colony repeatedly indicated that each problem that occurred impacted its schedule and costs. 

A Contractor That Acts as His Own Expert Witness May Inadvertently Waive Attorney Client Privilege

The general rule is that a party does not have to disclose communications with its attorney seeking legal advice.  A recent Superior Court decision, Noble v. the City of Norwalk, 2012 Conn. Super. LEXIS 2017, however, has found an exception to the attorney client privilege that contractors need to be aware about.

During a trial, witnesses are not allowed to give their opinion unless they are qualified as an “expert.”  Under the legal definition, an “expert” is anyone that has knowledge through education, training or experience that would be helpful to the jury given the subject matter of the lawsuit.  Based upon the foregoing definition, almost anyone can qualify as an expert if the right case came along.  For example, my 13-year-old daughter has been taking ballet lessons since she was 3.  If ballet ever became relevant to a key issue in a lawsuit, my daughter would qualify as an expert on that subject.

In construction litigation, there are always questions that are not clearly fact or opinion.  For example, the amount of time that the forms have to remain in place after a concrete pour is a subject upon which there is disagreement and often depends upon the structure that was poured and the conditions under which the concrete was placed. 

Court Rules That the Government Contractor Defense is Not Applicable to Road Reconstruction Projects

As articulated by the United States Supreme Court, the government contractor defense provides that “[l]iability for design defects in military equipment cannot be imposed, pursuant to state law, when (1) the United States approved reasonably precise specifications; (2) the equipment conformed to those specifications; and (3) the supplier warned the United States about the dangers in the use of the equipment that were known to the supplier but not to the United States.”  Boyle v. United Techs. Corp., 487 U.S. 500, 512 (U.S. 1988).  The Connecticut Supreme Court recognized the government contractor defense in Miller v. United Technologies Corp., 233 Conn. 732 (Conn. 1995).  Nonetheless, a Connecticut Superior Court has just refused to apply the government contractor defense to a claim arising out of a road reconstruction project.

In Fox v. Town of Stratford, 2012 Conn. Super. LEXIS 1443 (Conn. Super. Ct. June 1, 2012), the plaintiff alleged that his property was damaged by flooding caused by a road reconstruction project.  The contractor asserted that, under the authority of Miller and Boyle, it cannot be held liable for plaintiff’s alleged damages because it strictly complied with the government’s plans and specifications.