A Contractor May Still Recover Monies Due For Work Performed Pursuant to an Unenforceable Contract

Despite what might appear to be the parties’ intentions, courts sometimes find contracts unenforceable.  Courts may find contracts unenforceable for any number of reasons including, but not limited to, the contract omitting a material term; the contract having vague or indeterminate terms; the contract violating the statute of frauds; the contract lacking consideration; and/or the contract not reflecting the understanding of both parties.  In those situations, a party that provides labor, materials, and/or services may still be entitled to receive payment for its work under the legal theories of unjust enrichment or quantum meruit.

“[U]njust enrichment and quantum meruit are alternative theories of restitution.”  Nation Elec. Contracting, LLC v. St. Dimitrie Romanian Orthodox Church, 144 Conn.App. 808, 814, 74 A.3d 474, 478 (Conn.App., 2013).  “Unjust enrichment applies whenever justice requires compensation to be given for property or services rendered under a contract, and no remedy is available by an action on the contract.”  Gagne v. Vaccaro, 255 Conn. 390, 401, 766 A.2d 416, 424 (Conn.,2001).  “Quantum meruit is the remedy available to a party when the trier of fact determines that an implied contract for services existed between the parties, and that,

A Cautionary Tale for All Subcontractors

The Connecticut Appellate Court recently handed down a decision that should have all subcontractors carefully reviewing their subcontracts.  In Suntech of Connecticut, Inc. v. Lawrence Brunoli, Inc., 143 Conn. App. 581 (2013), Suntech of Connecticut, Inc. (“Suntech”) agreed to “provide glass doors, glass, glazing, an aluminum framing system, and a metal framing system” as a subcontractor on a state project.  Id.  As a result of an error in the plans and specifications, Suntech incurred substantial additional costs. Typically, when an error in the plans and specifications results in a contractor incurring additional costs, the contractor is entitled to a change order but that is not what occurred in this case.

The Suntech decision appears to go against two principles of Connecticut construction law.  First, in Southern New England Contracting Co. v. State, 165 Conn. 644, the Connecticut Supreme Court issued a decision consistent with the Spearin doctrine which states that, because the contractor agrees to build the project in accordance with the plans and specifications, the contractor will not be held responsible for damages should the plans and specifications end up being defective.  Second, while not conclusively determined,

Connecticut Statutes Provide Assistance with Receiving Prompt Payment on Public and Private Construction Projects

Under Connecticut law, an owner should pay its general contractor within 30 days of having received the general contractor’s application for payment; the general contractor, in turn, is required to pay its subcontractors and suppliers within 30 days of having received payment from the owner; and the subcontractors should then pay their sub-contractors and suppliers within 30 days of having received payment from the general contractor and so on down the line.  See Gen. Stat. § 49-41a and Conn. Gen. Stat. § 42-158j.

The provisions in § 49-41a and § 42-158j are substantially similar except that:

1.) Only private owners are required to make payment to their general contractors within a specified number of days after receiving an application for payment; and

2.) The statute only applies to public projects for which a payment bond is required, which is any public works project whose contract amount exceeds $100,000.

Both statutes also have similar enforcement procedures.  Either a subcontractor on a public project to which the statute applies or general contractors and subcontractors on a private project can make demand for payment by way of registered or certified mail and, within 10 days,

Another Step Closer to Understanding Pay-When-Paid Clauses

No provision in a standard construction contract has been more debated than the requirement for the general contractor to pay its subcontractors after its receipt of payment from the owner.  In situations where the owner does not pay the general contractor, the general contractor typically argues that it has no obligation to pay the subcontractor even if the reason for the owner’s nonpayment had nothing to do with the subcontractor.  Conversely, the subcontractor argues that – when the reason for the owner’s nonpayment is not the subcontractor’s fault – the general contractor must pay the monies the subcontractor is due.  Generally, the courts have said that contract language which states that the subcontractor shall not be paid until after the general contractor’s receipt of payment from the owner merely sets forth the time for payment and does not transfer the risk of the owner’s insolvency from the general contractor to the subcontractor.  “Normally and legally, the insolvency of the owner will not defeat the claim of the subcontractor against the general contractor.”  Sil/Carr Corp. v. Bartlett, 2012 Conn. Super. LEXIS 1665 (Conn. Super. Ct. June 26, 2012).  It is, however, possible for the contractor to transfer the risk of the owner’s nonpayment to the subcontractor. 

“Pay when Paid” versus “Pay if Paid”

Most subcontracts contain language, which state that the contractor shall pay the subcontractor within so many days after the contractor’s receipt of payment from the owner.  The question then becomes, “what happens if the owner never pays the contractor?”  It is a complicated question that has been the subject of much litigation.  The general rule is that – provided the owner is not withholding payment due to a failure by the subcontractor – the subcontract will be interpreted as requiring payment within a reasonable time. In other words, even if the owner does not pay the contractor for the subcontractor’s work, the contractor will still be expected to pay the subcontractor despite the fact that the subcontract requires the owner to first pay the contractor.

Of course, as with almost every legal issue, there are exceptions to the general rule.  For example, there are “magic words” that will make it more likely that the court will find that the subcontractor has given up its right to payment should the owner not pay the contractor.  Examples of such “magic words” are as follows:

• Contractor’s receipt of payment from owner is a “condition precedent” to the subcontractor’s right to payment;