Beware of No Damages for Delay Clauses

It is common for construction contracts to state that, if the project is delayed by the owner, the contractor shall be entitled to an extension of contract time but will not be entitled to any addition compensation.  Such a contract provision is known as a “no damages for delay” clause.  The Connecticut Supreme Court has held that “‘no damages for delay’ clauses are generally valid and enforceable and are not contrary to public policy. [unless]: (1) [the] delays [are] caused by the [owner’s] bad faith or its willful, malicious, or grossly negligent conduct, (2) [the delays] uncontemplated …, (3) [the] delays so unreasonable that they constitute an intentional abandonment of the contract …, and (4) [the] delays [result] from the [owner’s] breach of a fundamental obligation of the contract.  White Oak Corp. v. Department of Transp., 217 Conn. 281, 288-89, 585 A.2d 1199, 1203 (Conn.,1991).  The list of exceptions; however, may not actually be that broad.  In a recent decision, the Superior Court analyzed the applicability of the aforesaid exceptions to a typical “no damages for delay” clause.

In C & H Elec., Inc. v. Town of Bethel, an electrical contractor was substantially delayed because of the additional asbestos abatement work that was required.