The Importance of Reading and Understanding Your Construction Contract

Everyone knows that they ought to eat right and exercise; yet, far too few of us do it. Similarly, proper construction contract management requires a contractor to thoroughly understand their contracts but many fail to do so. Of course, the reason that contractors are often largely ignored are understandable. Most construction contracts have the same substantive provisions with which contractors are already familiar; the specific requirements for any given project will be discussed at the preconstruction meeting; and the more specific details of any contract tend to only really matter in the rare occasions that the parties end up in a dispute they cannot resolve on their own. However, the few instances that result in litigation may make having proper practices in place for every project worthwhile.

On a positive note, most contractors that I encounter are now reading their contracts before signing them, as opposed to only reading them after a problem develops. As obvious as this may sound, actually taking the time to thoroughly read a contract before a project begins is the only way to be certain that you will fully comply with all your obligations. In addition, reading a contract before signing can prevent a contractor from experiencing an unfortunate surprise.

Understanding Unabsorbed Home Office Overhead

It is readily apparent that – if a project is delayed – the contractor is losing money.  The increased direct costs associated with the labor and equipment on site are obvious. The more complex question arises when considering the effect a delayed project has on a contractor’s recovery of its home office overhead, where “home office overhead” is defined as the cost of the contractor’s main office including, but not limited to, rent, utilities, executive and management salaries, staff, office equipment, office supplies, taxes, insurance, etc.  Everyone intuitively understands that a delayed project increases such costs in the same manner that that delays increase the project’s direct costs but increases in home office overhead cannot be directly correlated to any one project because a contractor typically has several projects with overlapping schedules underway at any given time.  Over the years, courts have attempted to determine the damages necessary “to compensate a contractor for its indirect costs that cannot be allocated to a particular contract for the period during which the government has made contractual performance impossible.”  Charles G. Williams Constr., Inc. v. White, 326 F.3d 1376, 1380-1381 (Fed. Cir. 2003).  “As a result, there are at least nine formulas that have been used,

A Cautionary Tale for All Subcontractors

The Connecticut Appellate Court recently handed down a decision that should have all subcontractors carefully reviewing their subcontracts.  In Suntech of Connecticut, Inc. v. Lawrence Brunoli, Inc., 143 Conn. App. 581 (2013), Suntech of Connecticut, Inc. (“Suntech”) agreed to “provide glass doors, glass, glazing, an aluminum framing system, and a metal framing system” as a subcontractor on a state project.  Id.  As a result of an error in the plans and specifications, Suntech incurred substantial additional costs. Typically, when an error in the plans and specifications results in a contractor incurring additional costs, the contractor is entitled to a change order but that is not what occurred in this case.

The Suntech decision appears to go against two principles of Connecticut construction law.  First, in Southern New England Contracting Co. v. State, 165 Conn. 644, the Connecticut Supreme Court issued a decision consistent with the Spearin doctrine which states that, because the contractor agrees to build the project in accordance with the plans and specifications, the contractor will not be held responsible for damages should the plans and specifications end up being defective.  Second, while not conclusively determined,

Connecticut Statutes Provide Assistance with Receiving Prompt Payment on Public and Private Construction Projects

Under Connecticut law, an owner should pay its general contractor within 30 days of having received the general contractor’s application for payment; the general contractor, in turn, is required to pay its subcontractors and suppliers within 30 days of having received payment from the owner; and the subcontractors should then pay their sub-contractors and suppliers within 30 days of having received payment from the general contractor and so on down the line.  See Gen. Stat. § 49-41a and Conn. Gen. Stat. § 42-158j.

The provisions in § 49-41a and § 42-158j are substantially similar except that:

1.) Only private owners are required to make payment to their general contractors within a specified number of days after receiving an application for payment; and

2.) The statute only applies to public projects for which a payment bond is required, which is any public works project whose contract amount exceeds $100,000.

Both statutes also have similar enforcement procedures.  Either a subcontractor on a public project to which the statute applies or general contractors and subcontractors on a private project can make demand for payment by way of registered or certified mail and, within 10 days,

What to Do When You Don’t Have Time to Wait for a Written Change Order

One of the most litigated construction law issues is whether a contractor is entitled to payment for additional work performed without a fully executed written change order.  Most construction contracts state that the contractor is not entitled to payment for any additional work, unless the additional work is performed pursuant to a written change order that has been sign by the owner, contractor and the architect.  The problem is that — because time is money — waiting for a signed change order is often costly so most contractors move forward with additional work based upon verbal agreements with the intention of executing a written change order at a later date.

Most of the time, no problems arise from having performed additional work without first having a written change order.  The parties abide by their verbal commitments, which are then incorporated into the written change order required by the contract.  Once in a while, however, an owner will refuse to issue payment for work that was performed without a written change order despite an oral agreement being reached during the project.  In these situations, some courts have enforced the contract provision requiring written change orders and have denied the contractor the right to recover payment for his work.