A Cautionary Tale for All Subcontractors

The Connecticut Appellate Court recently handed down a decision that should have all subcontractors carefully reviewing their subcontracts.  In Suntech of Connecticut, Inc. v. Lawrence Brunoli, Inc., 143 Conn. App. 581 (2013), Suntech of Connecticut, Inc. (“Suntech”) agreed to “provide glass doors, glass, glazing, an aluminum framing system, and a metal framing system” as a subcontractor on a state project.  Id.  As a result of an error in the plans and specifications, Suntech incurred substantial additional costs. Typically, when an error in the plans and specifications results in a contractor incurring additional costs, the contractor is entitled to a change order but that is not what occurred in this case.

The Suntech decision appears to go against two principles of Connecticut construction law.  First, in Southern New England Contracting Co. v. State, 165 Conn. 644, the Connecticut Supreme Court issued a decision consistent with the Spearin doctrine which states that, because the contractor agrees to build the project in accordance with the plans and specifications, the contractor will not be held responsible for damages should the plans and specifications end up being defective.  Second, while not conclusively determined,

Restarting the 90 Day Clock to File a Mechanic’s Lien

As most contractors are aware, in Connecticut, you have 90 days after the last day that you supply labor and/or materials to file a mechanic’s lien.  Many other states have the same or a similar requirement pertaining to when a mechanic’s lien can be filed.  The question that is often asked is which “last day” starts the clock.

In a common scenario, additional work is performed more than 90 days after what was originally thought to be the last day worked and the contractor then claims that the second last day starts a new 90 days clock to file a mechanic’s lien.  Sometimes such mechanic’s liens are upheld but they are typically invalidated.  The reason is that the typical scenario involves a contractor – who has not been paid – realizes that his time to file a mechanic’s lien has expired so he returns to the site to perform a minor punchlist item that was inadvertently left undone initially.  Generally speaking, to restart the mechanic’s lien clock, a contractor must perform substantive work that was authorized by the owner or someone rightfully acting on the owner’s behalf.  The most recent guidance on this issue was provided by the Connecticut Appellate Court in Cianci v.

Subcontractors Only Have Very Limited Rights Against Public Owners

On private construction projects, subcontractors and/or suppliers that furnish labor, material, or services but are not paid by the project’s general contractor have a variety of claims that they may assert against a private owner.  For example, such subcontractors and/or suppliers may assert claims for unjust enrichment or file a mechanic’s lien.  No such rights exist, however, where the project owner is the State of Connecticut or one of its cities or towns.

As an alternative to the typical claims a subcontractor or supplier has against a private owner, Conn. Gen. Stat. § 49-41 requires general contractors that enter contracts for public projects over a certain dollar amount to post surety bonds that guarantee payment to their subcontractors and suppliers.  The exact language of Conn. Gen. Stat. § 49-41 states that “[e]ach contract . . . [for] any public building or public work of the state or a municipality shall include a provision that the person to perform the contract shall furnish . . . a bond . . . for the protection of persons supplying labor or materials . . .”  By the plain language of the statute, the onus is put on the general contractor to supply the bond;

A Contractor That Acts as His Own Expert Witness May Inadvertently Waive Attorney Client Privilege

The general rule is that a party does not have to disclose communications with its attorney seeking legal advice.  A recent Superior Court decision, Noble v. the City of Norwalk, 2012 Conn. Super. LEXIS 2017, however, has found an exception to the attorney client privilege that contractors need to be aware about.

During a trial, witnesses are not allowed to give their opinion unless they are qualified as an “expert.”  Under the legal definition, an “expert” is anyone that has knowledge through education, training or experience that would be helpful to the jury given the subject matter of the lawsuit.  Based upon the foregoing definition, almost anyone can qualify as an expert if the right case came along.  For example, my 13-year-old daughter has been taking ballet lessons since she was 3.  If ballet ever became relevant to a key issue in a lawsuit, my daughter would qualify as an expert on that subject.

In construction litigation, there are always questions that are not clearly fact or opinion.  For example, the amount of time that the forms have to remain in place after a concrete pour is a subject upon which there is disagreement and often depends upon the structure that was poured and the conditions under which the concrete was placed. 

The Contract and Not Common Sense Determines the Proper Parties to an Arbitration

Many construction contracts require the parties to resolve their disputes through alternate dispute resolution procedures such as mediation and arbitration.  Arbitration is intended to be a cost effective alternative to litigation.  The issue of whether arbitration works as well as intended will be the subject of a future post on this Blog but the topic of discussion here is the question of determining the proper parties to any given arbitration.  The answer is counterintuitive.

When it comes to arbitration, there are several well settled rules.  For example, courts favor arbitration, arbitration is a creature of contract, and no party will be forced to arbitrate when it has not agreed to do so.  In light of the foregoing, you might believe that a party, who is named in a demand for arbitration, files an answer to the demand, and participates in the arbitration hearing, has agreed to arbitrate and should be held liable for any arbitrator’s award that enters against it.  If you did believe that, however, you’d be wrong.

In CDIFUND, LLC v. Lenkowski, disputes arising out of home construction contracts were arbitrated.  CDIFUND, LLC v. Lenkowski, 2011 Conn. Super.

The Standard Procedure for Obtaining Lien Waivers May Be Ineffective

A recent Superior Court decision should cause general contractors and owners to reevaluate their procedures for obtaining lien waivers.  Typically, signed lien waivers are submitted after the work is performed but before payment is received.  On a basic level, the procedure makes sense because the owner does not want to issue payment to its general contractor unless it is sure that it’s protected from potential mechanic’s liens.  While the general contractor and its subcontractors may argue that they should not have to provide lien waivers until they receive payment, they are generally protected if the owner does not actually issue the payment described in the lien waiver because standard lien waiver language makes it clear that the waiver is not effective unless the payment described therein is actually received.

In Milone & MacBroom, Inc. v. Winchester Estates, 2011 Conn. Super. LEXIS 2688, the Superior Court considered whether a lien waiver is valid when:

1. The lien waiver is issued after the work is performed:
2. The lien waiver is executed before payment is received; and
3. The payment described in the lien waiver is received three weeks after the lien waiver was signed.

Court Rules That the Government Contractor Defense is Not Applicable to Road Reconstruction Projects

As articulated by the United States Supreme Court, the government contractor defense provides that “[l]iability for design defects in military equipment cannot be imposed, pursuant to state law, when (1) the United States approved reasonably precise specifications; (2) the equipment conformed to those specifications; and (3) the supplier warned the United States about the dangers in the use of the equipment that were known to the supplier but not to the United States.”  Boyle v. United Techs. Corp., 487 U.S. 500, 512 (U.S. 1988).  The Connecticut Supreme Court recognized the government contractor defense in Miller v. United Technologies Corp., 233 Conn. 732 (Conn. 1995).  Nonetheless, a Connecticut Superior Court has just refused to apply the government contractor defense to a claim arising out of a road reconstruction project.

In Fox v. Town of Stratford, 2012 Conn. Super. LEXIS 1443 (Conn. Super. Ct. June 1, 2012), the plaintiff alleged that his property was damaged by flooding caused by a road reconstruction project.  The contractor asserted that, under the authority of Miller and Boyle, it cannot be held liable for plaintiff’s alleged damages because it strictly complied with the government’s plans and specifications. 

Subcontractors Only Have Very Limited Rights Against Public Owners

On private construction projects, subcontractors and/or suppliers that furnish labor, material, or services but are not paid by the project’s general contractor have a variety of claims that they may assert against a private owner.  For example, such subcontractors and/or suppliers may assert claims for unjust enrichment or file a mechanic’s lien.  No such rights exist, however, where the project owner is the State of Connecticut or one of its cities or towns.

As an alternative to the typical claims a subcontractor or supplier has against a private owner, Conn. Gen. Stat. § 49-41 requires general contractors that enter contracts for public projects over a certain dollar amount to post surety bonds that guarantee payment to their subcontractors and suppliers.  The exact language of Conn. Gen. Stat. § 49-41 states that “[e]ach contract . . . [for] any public building or public work of the state or a municipality shall include a provision that the person to perform the contract shall furnish . . . a bond . . . for the protection of persons supplying labor or materials . . .”  By the plain language of the statute, the onus is put on the general contractor to supply the bond;

Don’t Get Creative When Attempting To Enforce Mechanic’s Lien Rights

In Connecticut, the law pertaining to mechanic’s liens is well settled.  You will not come across many issues of first impression while trying to enforce a mechanic’s lien and, therefore, practitioners should not attempt to drive the proverbial square peg into a round hole.  Such an attempt was made (and failed) in a matter recently decided by the Connecticut Superior Court.

In that case, an assignee of a mortgage brought a foreclosure action and named a contractor as a defendant because the contractor’s mechanic’s lien was subsequent in right to the interest being foreclosed.  Normally, if the property proceeds all the way through the foreclosure process, a contractor holding a subordinate lien allows his interest in the property to expire because the only way to maintain the lien is to pay off the foreclosing mortgage but , in this case, the contractor did not give up that easily.

Here, the contractor alleged that the assignee became the “owner” of the property by virtue of the construction mortgage and, as such, was responsible to pay for the work that the contractor performed.  The court identified 2 issues that allowed the court to dispose of the contractor’s claim on summary judgment.