In Girolametti v. Michael Horton Assocs., Inc., the Supreme Court determined when a subcontractor’s rights will be affected by an arbitration in which the subcontractor did not participate. Girolametti v. Michael Horton Assocs., Inc., 332 Conn. 67, 71 (2019). This decision was based upon “the rule of claim preclusion,” which prevents the re-litigation of a claim once the claim has had a full and fair hearing “regardless of what additional or different evidence or legal theories might be advanced in support of it.” Id. at 75. In order for claim preclusion to apply, the following requirements must be met:
(1) The prior judgment must have been rendered on the merits by a court of competent jurisdiction;
(2) The parties to the prior and subsequent actions must be the same or in privity;
(3) There must have been an adequate opportunity to litigate the matter fully; and
(4) The same underlying claim must be at issue.
Id. After applying these requirements in Girolametti, the Supreme Court held that the owner’s claims against the subcontractors were barred because they were either brought or could have been brought in the owner’s arbitration against the general contractor.
The general rule is that a party does not have to disclose communications with its attorney seeking legal advice. A recent Superior Court decision, Noble v. the City of Norwalk, 2012 Conn. Super. LEXIS 2017, however, has found an exception to the attorney client privilege that contractors need to be aware about.
During a trial, witnesses are not allowed to give their opinion unless they are qualified as an “expert.” Under the legal definition, an “expert” is anyone that has knowledge through education, training or experience that would be helpful to the jury given the subject matter of the lawsuit. Based upon the foregoing definition, almost anyone can qualify as an expert if the right case came along. For example, my 13-year-old daughter has been taking ballet lessons since she was 3. If ballet ever became relevant to a key issue in a lawsuit, my daughter would qualify as an expert on that subject.
In construction litigation, there are always questions that are not clearly fact or opinion. For example, the amount of time that the forms have to remain in place after a concrete pour is a subject upon which there is disagreement and often depends upon the structure that was poured and the conditions under which the concrete was placed.