Connecticut Statutes Provide Assistance with Receiving Prompt Payment on Public and Private Construction Projects

Under Connecticut law, an owner should pay its general contractor within 30 days of having received the general contractor’s application for payment; the general contractor, in turn, is required to pay its subcontractors and suppliers within 30 days of having received payment from the owner; and the subcontractors should then pay their sub-contractors and suppliers within 30 days of having received payment from the general contractor and so on down the line.  See Gen. Stat. § 49-41a and Conn. Gen. Stat. § 42-158j.

The provisions in § 49-41a and § 42-158j are substantially similar except that:

1.) Only private owners are required to make payment to their general contractors within a specified number of days after receiving an application for payment; and

2.) The statute only applies to public projects for which a payment bond is required, which is any public works project whose contract amount exceeds $100,000.

Both statutes also have similar enforcement procedures.  Either a subcontractor on a public project to which the statute applies or general contractors and subcontractors on a private project can make demand for payment by way of registered or certified mail and, within 10 days,