Are Contractors and Subcontractors Allowed to Rob Peter to Pay Paul When it Comes to Paying Subcontractors and Suppliers?

One of the main problems most contractors (and subcontractors) face is cashflow. When the economy is going well, most contractors still find their payments lagging 60 to 90 days behind the 30 days required by most construction contracts. When an owner fails to make timely payment, general contractors end up in arrears with their subcontractors, who end up in the arrears with their subcontractors (i.e. sub-subcontractors) and suppliers. Often well intended contractors (and subcontractors) may end up using monies received from one project to pay subcontractors (and/or sub-subcontractors) on another. The reasons for paying subcontractors from one project with funds received from another may be because the subcontractors on the second job have gone longer without payment and/or are more in need. The question is whether that is legal.

In Connecticut, it has recently become riskier for contractors to pay their subcontractors (and for their subcontractors to pay their sub-subcontractors and suppliers) with funds received from another project. Connecticut has long had prompt payment statutes which require contractors to pay subcontractors “not later than twenty-five days after the date the contractor receives payment from the owner” on private projects and “within thirty days after payment to the contractor by the state or a municipality” on public projects.

WHAT TO DO WHEN YOU ARE NOT BEING PAID

The most common issue I confront as a construction attorney is what to do when my client is not being paid. The standard approaches include sending a demand letter, making a demand for disputed funds to be placed in escrow in accordance with the prompt payment statute, and, of course, filing mechanic’s liens and/or bond claims. The larger issue becomes what to do when my client can no longer to perform its work without payment.

As a general rule, a contractor is better off completing its work, and then fighting about the monies due, as opposed to walking off the job. While it is true that there are Connecticut cases which hold that a contractor is excused from finishing its work if progress payments are not made when due, but reliance on such cases is fraught with potential problems.

If you ever forced to litigate, you want to be viewed as the one wearing the white hat. You want to be the injured party that is as pure as the driven snow. If at all possible, you do not want to give the other side any arguments to raise. Thus, if you walk off the job for nonpayment,

With Payment Bond Claims, Different Rules Apply to the Bond Claimant and the Surety

As previously discussed in this Blog, Conn. Gen. Stat. § 49-41 requires each general contractor on a public works projects valued over $100,000 to post a payment bond that guarantees payment to the general contractor’s subcontractors and suppliers.  The payment bond also guarantees payment to each subcontractors’ sub-subcontractors and suppliers.

The procedure by which such subcontractors, sub-subcontractors, and/or suppliers may make claim against such payment bonds is described in Conn. Gen. Stat. § 49-42.  With the exception of claims for retainage, the statute requires those making claim on the payment bond to submit their “notice of claim” within 180 calendar days after the last day that it worked and/or supplied materials.  The statute then provides the surety that issued the payment bond with 90 calendar days to pay or deny the claim.  Until recently, both time provisions were mandatory.  See Barreira Landscaping & Masonry v. Frontier Ins. Co., 47 Conn. Supp. 99, 110, 779 A.2d 244, 252 (Super. Ct. 2000)(holding that both the notice of claim and the surety’s response both much be made within the time specified by statute.)

With regard to the 90 day time limit, the court in Barreira Landscaping &