Most Construction Disputes Do Not Involve Unfair Trade Practices

Generally speaking, the legal profession is not currently held in high esteem. In my opinion, there are a couple of reasons for this situation. First, I believe that the general public does not fully understand the adversarial process used in our legal system or the reasons why lawyers are allowed to “argue in the alternative,” which, in normal parlance, would negatively be referred to as talking out of both sides of your mouth. Second, the negative public opinion is (unfortunately) deserved by virtue of how some attorneys approach their cases.

Attorneys that draft complaints that go beyond any reasonable interpretation of the facts hurt themselves and the legal profession as a whole. I once received a complaint that was far beyond the pale because, in a case where a subcontractor asserted a claim for nonpayment, the attorney not only alleged breach of contract, but also asserted a human rights violation against my client because the subcontractor was a Minority Business Enterprise (“MBE”) and my client was allegedly a racist. Of course, my African American client and I had a good laugh when I called to let her know that she was being accused of being a racist. (Practice tip to new attorneys: If you are going to make a claim based upon race,

IN CASE YOU WERE WONDERING, MECHANIC’S LIENS AND PAYMENT BONDS REALLY DO PROTECT THOSE THAT SUPPLY LABOR, MATERIALS AND/OR SERVICES

In poker, you have to play the cards you are dealt, but, if you have a bad hand, you can fold. In litigation, if you do not have a strong argument, you should negotiate a settlement, but that is not always possible because the opposing party’s demands may be so unreasonable that you might as well go to trial and see what happens. It is at those times where an attorney might attempt to get creative. Recently, our Appellate Court upheld a trial court decision that held a surety liable on both a payment bond and a mechanic’s lien substitution bond despite the nine special defenses that it raised. See O & G Indus. v. Am. Home Assur. Co., 204 Conn. App. 614 (2021). Some of these special defenses were novel, and, as a result, this decision gives us some greater insight into lien and bond claims.

In O & G Indus. v. Am. Home Assur. Co., the plaintiff brought an action against a surety that had issued both the subject project’s payment bond and a bond that was substituted for the plaintiff’s mechanic’s lien. Id. By way of brief background,

Are Contractors and Subcontractors Allowed to Rob Peter to Pay Paul When it Comes to Paying Subcontractors and Suppliers?

One of the main problems most contractors (and subcontractors) face is cashflow. When the economy is going well, most contractors still find their payments lagging 60 to 90 days behind the 30 days required by most construction contracts. When an owner fails to make timely payment, general contractors end up in arrears with their subcontractors, who end up in the arrears with their subcontractors (i.e. sub-subcontractors) and suppliers. Often well intended contractors (and subcontractors) may end up using monies received from one project to pay subcontractors (and/or sub-subcontractors) on another. The reasons for paying subcontractors from one project with funds received from another may be because the subcontractors on the second job have gone longer without payment and/or are more in need. The question is whether that is legal.

In Connecticut, it has recently become riskier for contractors to pay their subcontractors (and for their subcontractors to pay their sub-subcontractors and suppliers) with funds received from another project. Connecticut has long had prompt payment statutes which require contractors to pay subcontractors “not later than twenty-five days after the date the contractor receives payment from the owner” on private projects and “within thirty days after payment to the contractor by the state or a municipality” on public projects.

NEGOTIATING A CONSTRUCTION CONTRACT CLAIM CAN FEEL LIKE LEGALIZED EXTORTION

Contractors often end up with monetary claims for nonpayment, changed conditions and/or additional work that are difficult to negotiate. Such claims are often met with counterclaims for defective work, and/or contractual defenses such as lack of notice and/or the lack of a written change order. Defeating such counterclaims are often difficult, but, when it comes to negotiating a settlement of a contractor’s monetary claim, the real difficulty is with the potential attorneys’ and/or costs associated with litigation or arbitration. Even a contractor with a six figure claim amount must seriously consider the attorney’s fees associated with litigating a matter to a final judgment or award in addition to the costs associated with the time its organization spends preparing for and attending any dispute resolution proceeding not to mention the risks associated with putting your fate in the hands of a third party whether that be a judge, jury or arbitration panel.

Anyone who has participated in a mediation has likely heard a mediator say, “Well, if you don’t like that offer, you are going to have to pay your attorneys a majority and/or all of the difference between your claim amount and what is being offered now, and,

HERE’S AN UPDATE ON THE EFFECT OF PRIOR RULINGS ON SUBSEQUENT LITIGATION

In a prior post, this blog explained how the Supreme Court held that an owner’s claims against subcontractors were barred because they were either brought or could have been brought in the owner’s prior arbitration against the general contractor. Girolametti v. Michael Horton Assocs., Inc., 332 Conn. 67, 71 (2019). The court ultimately determined that the contractual relationship between a general contractor and its subcontractors was sufficient to determine that they were “sharing the same legal right.” Therefore, “the rule of claim preclusion,” which prevents the re-litigation of a claim once the claim has had a full and fair hearing “regardless of what additional or different evidence or legal theories might be advanced in support of it,” applied in this case even though the subcontractors did not participate in the arbitration. Id. at 75.

Girolametti involved a situation where the dispute between the owner and general contractor included claims that the work performed by subcontractors was defective. Although the subcontractors were not parties to the arbitration, they were no doubt happy with the result and more than willing to have that decision applied to the owner’s subsequent lawsuit against them.

In my prior post,

A RECENT SUPREME COURT DECISION DRAMATICALLY AFFECTS SUBCONTRACTORS’ RIGHTS

In Girolametti v. Michael Horton Assocs., Inc., the Supreme Court determined when a subcontractor’s rights will be affected by an arbitration in which the subcontractor did not participate. Girolametti v. Michael Horton Assocs., Inc., 332 Conn. 67, 71 (2019). This decision was based upon “the rule of claim preclusion,” which prevents the re-litigation of a claim once the claim has had a full and fair hearing “regardless of what additional or different evidence or legal theories might be advanced in support of it.” Id. at 75. In order for claim preclusion to apply, the following requirements must be met:
(1) The prior judgment must have been rendered on the merits by a court of competent jurisdiction;
(2) The parties to the prior and subsequent actions must be the same or in privity;
(3) There must have been an adequate opportunity to litigate the matter fully; and
(4) The same underlying claim must be at issue.
Id. After applying these requirements in Girolametti, the Supreme Court held that the owner’s claims against the subcontractors were barred because they were either brought or could have been brought in the owner’s arbitration against the general contractor.

When the Breach of a Construction Contract is not a Breach

The doctrine of substantial performance holds that a contractor’s breach of a construction contract does not entitle the owner to damages because the contractor’s performance was close enough to that which the contract required. “Technical violations are excused not because compliance [is] impossible, but because actual performance is so similar to the required performance that any breach that may have been committed is immaterial. Substantial performance occurs when, although the conditions of the contract have been deviated from in trifling particulars not materially detracting from the benefit the other party would derive from a literal performance, [the other party] has received substantially the benefit [it] expected, and is, therefore, bound to perform.” United Concrete Prod., Inc. v. NJR Constr., LLC, No. CV176011932S, 2018 WL 5733720, at *4 (Conn. Super. Ct. Oct. 17, 2018). The classic example of this doctrine is a situation where the contract specifies a product manufactured by Company A but the contractor provides the same product manufactured by Company B. Because the contract expressly stated that the product shall be manufactured by Company A, the installation of the same product manufactured by a different company is a breach of the contract. However, because the products are identical other than the name of the manufacturer,

Connecticut’s Procedure for Substituting a Bond for a Mechanic’s Lien Needs to be Changed

The purpose of a mechanic’s lien is to provide collateral for a contract debt. If you perform work on a project and are not paid, then the mechanic’s lien laws allow you to attach the property where the work was performed. In other words, a mechanic’s lien provides you with a property right you can foreclose in the same manner a bank can foreclose a mortgage. However, before you can force a sale of the property to collect your money, you have to prove you are entitled to the payment you claim. Therefore, a mechanic’s lien could be in place a long time.

Because the lien laws are intended to provide security for a debt, but are not intended to prevent the property from being transacted, most states, including Connecticut, have a procedure by which a surety bond can be substituted for a mechanic’s lien. The problem with Connecticut’s procedure is that it is too long and cumbersome.

While a mechanic’s lien is in place, a property cannot be refinanced, or sold – at least not without addressing the mechanic’s lien to a lender’s and/or buyer’s satisfaction. It is possible that the property might be refinanced or sold if the owner places the lien amount in escrow,

The Importance of Reading and Understanding Your Construction Contract

Everyone knows that they ought to eat right and exercise; yet, far too few of us do it. Similarly, proper construction contract management requires a contractor to thoroughly understand their contracts but many fail to do so. Of course, the reason that contractors are often largely ignored are understandable. Most construction contracts have the same substantive provisions with which contractors are already familiar; the specific requirements for any given project will be discussed at the preconstruction meeting; and the more specific details of any contract tend to only really matter in the rare occasions that the parties end up in a dispute they cannot resolve on their own. However, the few instances that result in litigation may make having proper practices in place for every project worthwhile.

On a positive note, most contractors that I encounter are now reading their contracts before signing them, as opposed to only reading them after a problem develops. As obvious as this may sound, actually taking the time to thoroughly read a contract before a project begins is the only way to be certain that you will fully comply with all your obligations. In addition, reading a contract before signing can prevent a contractor from experiencing an unfortunate surprise.